| Manjung Power Plant Aug 2001
 
 Malaysia's newest power project, the
        Manjung Power Plant, is located on the West coast of
        Peninsular Malaysia, 260 km north of Kuala Lumpur in
        Perak. It will also be the largest coal fuelled power
        station in the country. TNBJ, the national power utility,
        awarded a turnkey design and construct contract to a
        joint venture between Alstom and Peremba with the civil
        engineering works being carried out by Leighton
        Contractors Malaysia.
 The power plant
        project is being built on a 'Power Island' just off the
        coast to allay environmental concerns. The recently
        reclaimed island is to be the site of the 3 x 700 MW
        plant. One of the most time critical structures of the
        project was the pump house and associated water pond.
        However, its design was complicated by the geology of the
        site. Although not far from the mainland, the reclaimed
        sand platform sits on soft marine clays overlying recent
        alluvial deposits, making it complex to excavate the 20 m
        deep sea water intake and pumping station in future. The
        initial design envisaged a sheet pile cofferdam. However,
        from a practical point of view the numerous strut levels
        would have made excavation and construction costly and
        very time consuming. Specialist geotechnical contractor
        Bachy Soletanche Malaysia developed an alternative scheme
        for the construction of the pump house which was adopted
        by the engineer in the ultimate design.
 
  Figure of eight shaft -61 & 59m diameter
        with depths 30-40m
 The solution consisted of using a diaphragm wall
        retaining wall to form the water pool and the pump house
        without any need for internal strutting. This was done by
        creating a figure of eight shape, with one section for
        the water pool and the other slightly larger section for
        the pump house proper. The figure of eight shaft
        consisted of two touching circles which are 61 m and 59 m
        in diameter with panel depths of 30 to 40 m deep. The use
        of the diaphragm wall to contribute load bearing capacity
        meant that only 31 barrettes foundations, 60 m deep, were
        required to found the heavy pump house structure and
        equipment. This also contributed to the savings in time
        as initially eighty large diameter bored piles had been
        anticipated. The diaphragm wall and foundation work was
        completed in about 12 weeks between June to August 2000.
        This allowed the rapid excavation of the water pool and
        pump house and the construction and installation of the
        critical mechanical equipment. 
 However, while the design is very efficient, the
        construction of any circular shaft needs to be carried
        out in accordance with strict tolerances to ensure the
        highest quality of work. Due to the nature of the
        circular retaining structures, their efficiency derives
        from the hoop action of the compressive forces. This
        means that the accuracy of the diaphragm wall panel
        joints must be controlled to ensure that the compressive
        forces are transmitted between the two structural
        elements. Any deviation between the panels reduces the
        surface area available and therefore the capacity of the
        hoop structure to resist the forces. To ensure compliance
        with the strict 1:200 tolerances, Bachy Soletanche
        Malaysia used the highly accurate KS3000 hydraulic grab
        to excavate the diaphragm wall panels and barrettes.
        Incorporated in the grab is an inclinometer that gives
        real time readout in the operator's cab showing the
        verticality in both planes. Any deviation outside can
        immediately be corrected. The KS3000 equipment is used
        regularly in Malaysia, Indonesia and Singapore but
        normally for its high productivity rate. This was one of
        the first instances it was used in Asia for such
        tolerance critical work. The compressive forces discussed
        above come together for both shafts at the two
        intersection points  another quality critical
        point.
 Apart from the delicate excavation of these two Y shaped
        panels, the reinforcement cage detail was very important.
        For ease of construction and installation, the 'cage'
        consisted of four elements, a triangular central cage and
        three normal reinforcement cages for each leg'. All four
        elements had to be overlapping which made for complex
        manoeuvring of cranes on site." To enable the
        accurate placing of all this reinforcement, the
        triangular or 'spider' cage was placed in the
        intersection of the Y with its legs' extending to each
        side of the panel. Next the three normal reinforcement
        cages were lowered into each leg of the Y, interlocking
        with the triangular cage, which acted as a guide. Once
        all the cages were safely and accurately installed in the
        panel, universal beams were then placed in the pump house
        and water pool sides of the Y panel to further reinforce
        this 'pinch' point. Concreting was undertaken using three
        tremie pipes which were filled together to ensure the
        highest quality finish. In addition to these two special
        panels, there were a number of other special panels for
        the water intake tunnels and the pipe work leading to the
        power station from the pump. To ensure structural
        integrity around the future openings, specially designed
        reinforcement panels were installed into the wall. This
        innovative design and construction method is the first
        such application in Southern Asia, according to Bachy
        Soletanche. Similar but smaller projects of this nature
        have been carried out by Bachy Soletanche in Hong Kong
        and Korea.
 
 The advantages to the programme and structure were
        significant. With the retaining structures being
        incorporated into the permanent works, further cost
        savings were obtained. Such structures are often used in
        Europe for storm water retention as the highly efficient
        design and the rapid construction time ensures minimum
        disruption to the surrounding properties. The equipment
        used incorporates sophisticated electronic and hydraulic
        systems, is reliable, and adapted to the works of this
        nature. It is a reliable alternative to the Hydrofraise
        diaphragm wall cutter for accuracy.
 Extract from Southeast Asia Construction. |